Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome – Winter – 2023/2024 – Building Of The Dome Structure Continues

Spring of 2020 – Conceptional Ideas Come to Life on SketchUp

Original Design of our 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome
Original Design

During the spring of 2020 Michael purchased the 3D Modelling Program SketchUp and began designing our 5 Partial Sphere 3 Frequency Icosahedron Dome.

Because of post-COVID inflation rates we are not building the annex and main dome (dome to the left). We have chosen to build the garage and workshop section of the original design, with a studio apartment above to call home.


Updated design of our Dome Home
Updated design of our Dome Home

Interior design of our Dome Home
Interior design of our Dome Home

Two years after he started putting his ideas into 3D form, construction begins with Michael as the one man general contractor.

Michael has designed, researched, organized, been part of or is building every aspect of our dome.

We hope you enjoy this blog series.

You can contact us at info@joyfulstephanie.me for further information or questions.

Stephanie & Michael

December – Building the Top of the Dome & First Sheathing

Using a scissor lift, Michael – with a few days help from Tyler – completed the top portion of the dome.

January – Weather Slows Michael Down

January 1st, 2024 - East Hants, Nova Scotia - Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome
January 1st, 2024
January 29th, 2024 - East Hants, Nova Scotia - Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome -
January 29th

December 1st, 2023 & January 1st, 2024 – Progress Comparison

January – 2024

January 1st, 2024 - East Hants, Nova Scotia - Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome

These are two of my favourite photos of the dome.

What was actually happening on that starlit beautiful evening was not that fun. It was very cold while Michael and I unloaded plywood from the back of the truck.


January 29th, 2024 - East Hants, Nova Scotia - Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome - Another snow storm
January 29th – Another snow storm

February

Michael shovelled A LOT of snow off the slab. It was a daunting and frustrating task as a result of a few epic snowfalls. An example would be, in one storm up to 96cm of snow fell on some parts of Nova Scotia.


Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome – Concrete Wedges For Foundation Hubs & Family Help

Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome – Bolting Lower Struts To Hubs, Raising First Triangles & Installing Hub Sets

Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome – November, 2023 – Building the Dome Structure

Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome – Winter – 2023/2024 – Building Of The Dome Structure Continues

Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome – Spring – 2024 – Framing Trapezoids

Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome – Spring – 2024 – Drone Photos Of Penny Lane

Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome – Landscaping & Sheathing & Window Framing

Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome – Construction Of The North Entrance Portico

Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome – Applying The Elastomeric Membrane

Building A 5 Partial Sphere 3 Frequency Icosahedron Geodesic Dome – Progress From January To June 2025